Solar panels on a farm

A farm has roofs and fields that can carry solar panels. Before any are fitted, the farmer works through planning, the connection to the grid, and how the panels will be treated for business rates.

Panels on a farm building roof

In England, solar panels on the roof of a building that is not a house or a block of flats can often go up without a planning application. This is permitted development, under Class J of Part 14 of the permitted development order. Limits apply.

Larger roof systems, beyond microgeneration, come with an extra step. Before starting, the farmer must ask the council whether it needs to approve the design and appearance, including any glare for neighbours.

Whatever the size, the panels must be placed so they affect the look of the building and the area as little as practicable. They must be removed as soon as reasonably practicable once they are no longer needed.

A small stand-alone array in the yard

Class K allows one stand-alone solar unit within the grounds of a building that is not a house or flats. It must not be more than 4 metres high, or within 5 metres of the boundary. The panels must not cover more than 9 square metres, and no side of the array may be longer than 3 metres. Lower height limits can apply in conservation areas and other protected land, and the right does not cover the grounds of a listed building or a scheduled monument.

A solar farm in a field

For large solar farms on the ground, the government's planning guidance asks councils to weigh several things.

Connecting to the grid

Ofgem says a network operator is responsible for the pipes and wires that move energy. It points to the Energy Networks Association website to find your network operator.

National Grid Electricity Distribution, the regional electricity distribution part of National Grid, says its G98 procedures are for small generators of 16A (3.68kW) per phase or less. Larger ones, rated above 16A (3.68kW) per phase, follow its G99 procedures.

Business rates

GOV.UK lists agricultural land and buildings among the properties exempt from business rates. Solar panels can be treated differently.

The Valuation Office Agency's rating manual explains a rule for solar power used on site. In England, until 1 April 2035, renewable equipment is left out of the rateable value where its power is used within the property. The land and supports under it stay rateable. Wales has had the same rule since 1 April 2024.

Power sold to the grid is treated another way. Where most of the power is exported and the system is above 10 kilowatts, the manual says it will normally be a separate property needing its own assessment. Its example is a developer who rents a field for an array that supplies the grid.

Where panels sit on farm property that is otherwise exempt, the manual tells valuers to ask a specialist team for advice.

Useful links